State Funded Projects
Project Project Name Total Cost
Proj Manager Phase
980850 Environmental Sciences Building $ Banks Closeout
980450 Engineering Science Building 39,714,000 Monte Construction
980350 Life Sciences Building 32,379,000 Schwartzbach Construction
981240 Academic Building-State 55,272,000 Landfried P2003
981240 Academic Building-Donor 7,907,000 Landfried P2003
980000 Library Expansion 32,400,000 Wolever P2005
986031 Sewer System Renewal 4,718,000 Aronson Construction
988700 Snidecor Hall Office Wing Seismic Replacement 12,280,000 Castanha DD
981130 Psychology Building Addition 13,382,000 Eggemeyer CD
988620 Bio 2/ Noble Renovations 10,500,000 Eggemeyer SD
988720 Arts Building Seismic Corrections and Renewal 17,000,000 Eggemeyer P2004
980000 Ellison/Phelps Reno 6,971,000 Strahl P2006
980000 Public Safety 6,500,000 Strahl P2007
980000 Mesa Road 6,382,000 Strahl P2008
980000 Davidson Library Renewal 25,000,000 Wolever P2008
Total
$270,405,000
Non-State Funded Projects
Project Project Name Total Cost Proj Manager Phase
986255 Manzanita Village Student Housing Burrelsman Closeout
986255 MZV MP Building 2,200,000 Burrelsman Bid
986497 San Clemente Student Housing 116,702,000 Brown SD
986498 Residential Life Resource Center 3,235,000 Brown CD
98000 El Colegio Road 7,185,000 Brown
986265 Sierra Madre Student Housing 46,100,000 Brown Planning
980000 Faculty Housing 64,900,000 Brown Planning
980851 Marine Science Research Building 25,057,000 Banks Construction
981270 California Nanosystems Institute (PWC) 53,000,000 Monte BID
981270 Campus Parking Structure 2-Lot 10 16,409,000 Monte BID
981300 Intercollegiate Athletics Building 15,017,000 Van Thyne Construction
981400 Recreation Center Expansion 16,945,000 Burrelsman Construction
980000 Student Resource Building 24,522,000 Landfried CD
981320 Engineering II - 4th Floor Addition 4,000,000 Eggemeyer DPP
986455 DLG Seismic 12,500,000 Marini Construction
980000 Ortega Seismic 11,500,000 Marini CD
986465 Storke Family Student Housing Seismic Corrections and Renovations 80,000,000 Marini DD
988705 San Rafael Seismic 9,800,000 Marini Construction
981340 Kohn Hall Expansion 5,900,000 Aronson Construction
211-45 PSB-Eng.Mach. Shop Brown Feasibility
981440 MRL Expansion 4,500,000 Castanha CD
980000 Alumni Center 9,000,000 Castanha DPP
986600 CPS 3 20,250,000 Aronson SD
980000 Extended Learing - Aronson SD
988515 Francisco Torres Seismic 25,714,000 Strahl CD
Lagoon Road Drainage 600,000 Aronson Feasibility
SAASB HVAC/Water Intrusion 860,000 Castanha
East Gate Study Aronson Feasibility
Science Access Study Aronson Feasibility
SY Paving 250,000 Aronson Feasibility
Total $ 576,146,000
Grand Total $ 846,551,000


* Phase Legend

SD Schematic Design DD Design Development
CD Construction Documents P200x Preliminaries Complete in Future Year
DPP Detailed Project Program PPG Project Planning Guide
P Preliminaries W working drawings

Posted 030801